Upstream Inlet Air Cooling System for Rumaila Power Plant,Iraq

Upstream Inlet Air Cooling System for Rumaila Power Plant,Iraq

Client: MAPNA Group Plant Owner: Shamara Holding Location: Basra, Iraq Project Duration: 6 Month Commissioning Date: June 2023 Scope Of Work: EPC of Upstream Media Cooling system for two MGT70 GTs, each one with nominal Power of 185MW. Status: PAC Power increase: more than 18% on each GT @ design conditon . . Keywords: Upstream […]

More ...
New Contract Awarded “Media Cooling System for Rumaila Power Plant, Iraq”

New Contract Awarded “Media Cooling System for Rumaila Power Plant, Iraq”

Rahavard Energy has recently signed a contract of “Engineering, Procurement and Construction of Media Evaporative Cooling System for 2*MGT70 Gas Turbine Units of Rumaila Power Plant” in Basra City of Iraq. The client of this project is MAPNA Group and the plant owner is Shamara Holding. Rumaila Power Plant has 6 GTs in operation, each […]